Costitx is a small village with a small treatment works. Outside the village centre, the country houses and fincas have no sewer network and each deals with its own water. We are Joaquín and Juan, installers in Mallorca since 1998: we supply the new treatment plant, install it, do the electrics and prepare and sign the documents for your architect or engineer to submit.
Send us photos and details · Reply within 24-48 hours on working days · We assist you in English, Spanish and German
GRAF one2clean · Image: GRAF
Your village
Costitx sits on the Llubí groundwater body (1811M2), which it shares with Muro, Llubí, Inca, Sineu and Sencelles: 94 km² of the Pla de Mallorca.
According to Annex 9 of the Water Plan, the Llubí body is in poor chemical status because of nitrates, with 54 mg/l on average, and is slowly improving: in the previous cycle it was 57. The Plan puts this down to the vulnerable-zone programmes, applied here since 2000, and to there being less farming.
The body is also at risk because of chlorides (216 mg/l on average), and the Plan asks for abstraction and pump depth to be controlled. For a country house, this means looking after the well water, and that irrigating the garden with treated water, as art. 70.12 requires, is water that isn't pumped.
The aquifer is made of Miocene calcarenite, marl and reef limestone. You may hit rock when opening the pit; your builder will see it, and before they dig we give them in writing how the pit must be prepared according to the manufacturer of the unit.
The rules here
The unit has to be approved, CE-marked and compliant with the EN 12566 family (art. 70.14 of the Water Plan), and its manufacturer must certify a minimum performance of BOD₅ 70 %, COD 75 % and suspended solids 70 % (art. 70.10). We work with all brands; as an example, the GRAF one2clean.
The responsible declaration to the Direcció General de Recursos Hídrics (DGRH) is submitted with the unit installed (art. 70.4). For a new house on residential urban land without sewers, the prior notification to Recursos Hídrics comes first (Balearic Planning Act 12/2017, fourth transitional provision), and from then there are at most two years for the declaration (art. 70.5). The site of the unit has to take into account the ground, the slope and its position relative to the house (art. 70.7.b and c).
What we do
Sources: Balearic Water Plan, Royal Decree 49/2023 (regulations, art. 70, 71, 76 and 77) · Annex 9 of the Plan, entries for the groundwater body “Llubí (1811M2)” · EN 12566 · manufacturer's manual (GRAF one2clean, as an example).
How we work
Tell us what stage the house is at, the bed spaces, where the wells are, yours or the neighbours', and send us photos. With the location we see what that part of Costitx requires.
We send you in writing the unit, installation, electrics and documents. Your builder gets where and how to prepare the pit according to the ground, the slope and the manufacturer.
We install, commission and hand over the electrical certificate and the signed documents. Your architect or engineer files the declaration once the unit is installed.
Common questions
With the unit installed, the responsible declaration is submitted to the Direcció General de Recursos Hídrics (DGRH) (art. 70.4 of the Balearic Water Plan, Royal Decree 49/2023). The prior notification with its two-year period (art. 70.5) is for new houses on residential urban land without sewers (Balearic Planning Act 12/2017, fourth transitional provision); on rural land, whatever the building permit requires is handled by your architect with the town council. As the installation company we prepare and sign the unit's documents, and your architect or engineer submits them.
A new extended-aeration treatment plant, approved, CE-marked and compliant with EN 12566 (art. 70.14 of the Balearic Water Plan, Royal Decree 49/2023). We work with all brands; as an example, the GRAF one2clean. The model is chosen according to the number of bed spaces, whether the house is seasonal and what the part of Costitx where the plot lies requires.
The Water Plan requires the system to be sited without polluting groundwater and taking into account the ground and its position (art. 70.7.a to c of the Balearic Water Plan, Royal Decree 49/2023). That is why we ask you which wells there are, yours or neighbours', and where. Under Costitx, the Llubí body has 54 mg/l of nitrates according to Annex 9 of the Plan: what leaves the house has to leave treated.
Yes: the blower works 24 hours a day. We run the power line from the house's distribution board and fit a sealed outdoor sub-board next to the control cabinet, as a licensed low-voltage installation company, and hand over the electrical installation certificate. On a finca in Costitx with no mains electricity, the treatment plant is counted among the fixed loads when calculating the panels and batteries.
Yes. The responsible declaration to the Direcció General de Recursos Hídrics (DGRH) is always submitted, even below 12 population equivalents (art. 70.4 of the Balearic Water Plan, Royal Decree 49/2023). The only extra requirement above 12 is sending the performance checks and the sludge log every year (art. 70.11).
Keep learning
The general guide to treatment plants and what else we do in Costitx.
Septic tank, treatment plant or holding tank, the documents and maintenance, in detail.
See the guide →What a roof in Costitx produces according to PVGIS, the permits and the grants.
Solar panels in Costitx →Heating, hot water and cooling from one heat pump, and the FACTOR 2026 grant.
Heat pumps in Costitx →In the Pla and across Mallorca
Sewage treatment plants in the Pla de Mallorca: Montuïri · Vilafranca de Bonany · Sant Joan · Santa Eugènia · Maria de la Salut. Also nearby: Inca · Sencelles · Binissalem · Santa Maria del Camí, or see the guide to sewage treatment plants in Mallorca →
Need the house drainage (downpipes, rainwater, chambers)? Drainage in Mallorca →
Also in Costitx: air conditioning
See our work and customer reviews on the JSL Google Maps profile →
Quality
As an example, GRAF tanks. We propose the unit for each house and what the area requires.

Send us the location, the bed spaces, whether there are wells nearby and a few photos. We reply within 24-48 hours on working days.